Dock Permit in Fort Lauderdale
A dock permit in Fort Lauderdale runs through Broward County as well as the city. For a small private dock, the county has a shorter route called the general license. Here's what its bulletin says.
Does your dock fit the general license?
Check item 5 in the bulletin below. The dock has to be private and noncommercial, 500 square feet or less over the water, with no dredging or fill beyond what the pilings need.
Rebuilding an old one? Item 1 covers replacement, as long as the total doesn't grow past 500 square feet.
The bulletin says it's usually done within 7 to 10 days.
What the county wants to see
Drawings of the site as it is and as it'll be, a vicinity map and a survey. On a tidal canal it also asks for water and bottom elevations. You file through the ePermit portal, and there's a fee.
Who draws the plans? Ask the contractor when they call.
Over 500 square feet
Then the general license list doesn't cover it. Ask the contractor which county license applies instead. The state and the city have their own rules too: see the Florida dock permit exemption and Fort Lauderdale dock regulations.
What Broward County's bulletin says
Purpose
This Technical Bulletin is intended to clarify requirements and procedures for obtaining an Environmental Resource General License for the construction, addition and or repair of docks, seawalls and bulkheads in Broward County.
Overview
The process for obtaining a General License is a streamlined one, usually completed within 7-10 days. The general license process recognizes that certain minor projects present a limited environmental risk and the process required for obtaining a license has been simplified. Nevertheless, the process will ensure that necessary precautions are taken by the applicant to protect wetlands, water quality, public drinking water supply, fish and wildlife. Minor projects eligible for this streamlined process are described more fully below.
Discussion
The Urban Planning Division and Environmental Permitting Division regulate most construction activities in and around the waters of Broward County. These activities include dredging new lakes and canals, any work within a wetland area, work in, under and over on surface waters on projects such as, but not limited to, docks, seawalls, bulkheads, floating vessel platforms, boat lifts, piers and pilings. Section 27-336 of the Broward County Code allows for an Environmental Resource General License to be issued for certain minor work associated with the activities noted above. To be eligible for an Environmental Resource General License, the project must fall into one of the categories listed below. Upon successful completion of the process, plans will be approved, and a General Environmental Resource License is issued.
Eligible projects, items 1, 2 and 5 of 12
- The repair or replacement of existing docks, provided the new or repaired dock is not enlarged beyond a total of five hundred (500) square feet over-water surface area for the new and existing structure.
- The repair, maintenance, or restoration of existing functional seawalls no more than one (1) foot water ward of their original authorized location.
- The installation of private, noncommercial docks of five hundred (500) square feet or less of over-water surface area, where no dredging or filling is required except to install the pilings.
Application requirements
- A completed general license application submitted through the ePermit portal: www.broward.org/epermits
- Documents required:
- A vicinity map showing location and extent of the project as proposed.
- A plan view and cross-sectional drawing identifying the engineering and environmental conditions existing at the site.
- A plan view and cross-sectional view drawing identifying the engineering and environmental conditions as they are proposed to exist after the completion of the project.
- Mean high water elevations, mean low water elevations, and bottom elevations if the project is located in a tidal canal.
- A survey of the project site.
- A licensing fee applies and is payable online through the ePermit portal or by, cash check, or credit card. Checks should be made payable to the Broward County Board of County Commissioners.
Broward County Resilient Environment Department, Urban Planning Division. Technical Bulletin, April 2025: UPD Environmental Resource General License Requirements for Construction and Repair of Docks, Seawalls, Bulkheads. Bulletin (PDF). Pulled November 21, 2026.